Rockwall County’s road program is entering a new phase — with a new consultant, a larger management structure and several major transportation decisions now coming into focus.

HNTB is now providing program management services for the County’s Road Bond Program. Officials are also discussing an interim plan that could use John King Boulevard as a route for SH 205 through traffic, an Outer Loop public hearing is on the calendar, and NCTCOG has undergone a significant leadership change.

Taken together, the Sept. 16 Rockwall County Infrastructure Consortium meeting showed more than another round of road updates. Rockwall County is changing how its road bond program is managed while key projects and regional partnerships are shifting at the same time.

For residents, those decisions show up in commute times, school drop-off, construction delays and fuel costs. With substantially more public money now committed to the County’s road program, the question is straightforward:

What will residents see for the added cost?

What Rockwall County Is Now Paying to Manage Road Projects

For FY2026, Rockwall County budgeted $240,000 for transportation consulting services under its Road Improvements Bond fund. County transaction records show Innovative Transportation Solutions, or ITS, was being paid $20,000 per month under that arrangement.

Rockwall County has since moved away from ITS and selected HNTB as the program management consultant for the Rockwall County Road Bond Program.

The final negotiated costs are detailed in the Aug. 25, 2026 Rockwall County Commissioners Court packet. County General Counsel Daniel Ray’s memo lists $666,082 for the 12 month Basic Services task order$55,506.83 for the monthly Basic Services payment — and up to $336,198 for a 6 month Transition Plan.

The two authorized task orders total $1,002,280. Readers can review the underlying agreements in the same packet: Task Order 02 begins on page 140, and Task Order 01 begins on page 145.

For comparison, the $666,082 Basic Services amount is about 2.8 times the former $240,000 annual consulting budget. The scopes are not identical. However, HNTB’s assignment is broader and the separate $336,198 Transition Plan is temporary.

During the Aug. 25 Commissioners Court discussion, Commissioner Dana Macalik stated that the proposed contract was “three to four times larger than the current contract.” The Court approved the HNTB Master Agreement and Task Orders 1 and 2 on a 3-2 vote, with Commissioners Macalik and Lorne Liechty opposed. The motion also directed that the HNTB costs be paid from Crenshaw Road bond savings.

Crenshaw Road remains an active road bond project. The September Consortium report lists the northern portion as completed in October 2024 and says construction on the southern portion began Aug. 17, 2026, with completion currently projected for June 2027.

The County’s newly adopted FY2027 budget shows that the financial change extends beyond those two HNTB task orders.

Page 92 of the FY2027 adopted budget shows the former 081-800-410 Consulting Services line at $240,000 for FY2026. For FY2027, a separate 081-805-410 “Program Mgmt.” line carries $4,599,718 in the Road Improvements Bond fund.

That $4.6 million is not an HNTB contract. The two HNTB task orders identified above total just over $1 million, and the budget page does not break down everything included in the broader program management allocation.

What it does show is a substantially larger financial commitment to overseeing Rockwall County road projects.

ITS Remains in the September Report as HNTB Steps In

The September Consortium report captures the handoff from ITS to HNTB.

Although HNTB’s agreements became effective Sept. 1, several projects still reflect work handled by ITS before the transition.

For FM 552, TxDOT approved breakout limits proposed by Rockwall County and ITS. ITS also negotiated scope and fee with LTRA for Horizon Road/FM 3097 and with BGE for FM 551. An Aug. 10 FM 1141 kickoff included TxDOT, County staff, Commissioner Bobby Gallana and ITS.

Other projects already show HNTB stepping in. For the SH 66 interim intersection project, Consor was directed to coordinate with County staff and HNTB on scope and fee.

Edwards Road provides another example. After Rockwall County ended negotiations with Freese & Nichols, Commissioners approved a $1.385 million engineering agreement with Kimley-Horn on Aug. 25. The September report says a Notice to Proceed had been issued and that Kimley-Horn would coordinate with County staff and HNTB on the project kickoff.

The Edwards Road project calls for upgrading portions of the existing dirt roadway to a two lane concrete road using TRIP-08, TRIP-21 and Road & Bridge funding.

At the Sept. 16 meeting, HNTB also introduced its program management team and highlighted its local ties to Rockwall County.

John King Boulevard: From Local Repairs to a Regional Traffic Plan

One of the major September updates involves Future SH 205 Middle and John King Boulevard, a project that has been developing for years.

The County report says TxDOT, Rockwall County and the City of Rockwall confirmed the John King alignment as the locally and technically preferred alternative for SH 205 Middle in January 2017.

Now officials are discussing a more immediate step. The Regional Transportation Council, TxDOT, Rockwall County, the City of Rockwall and ITS are working on an MOU for an interim project that could use John King Boulevard as a route for SH 205 through traffic. A meeting was tentatively scheduled for Sept. 29.

The report also says NCTCOG included $8.8 million in the Transportation Improvement Program to reimburse Rockwall County for money previously spent on the Outer Loop environmental process. The County has indicated it would like those funds allocated instead to the SH 205 Middle/John King Boulevard project.

Future SH 205 Middle is currently estimated at approximately $67.9 million, with about $48.2 million in Category 2 construction funding identified. The report lists March 2027 for 100 percent plans and its current ready-to-let target.

The City of Rockwall’s Sept. 8 Council packet shows what that looks like on the ground, with before-and-after photographs of localized pavement repairs along John King Boulevard.

Residents are seeing repairs on the road they drive today while local and regional officials consider whether that same roadway could take on a much larger role carrying SH 205 through traffic.

For someone using John King to get to work, school, a doctor’s appointment or the grocery store, these decisions could affect the road they use every day. More traffic raises practical questions about intersections, capacity, pavement, maintenance and what improvements would need to accompany a larger regional role.

The City of Rockwall Was Present — But Not at the Table

Traffic and roadway activity on John King Blvd, photographed Aug. 29, 2026. Photo by Adrienne Balkum.
Traffic lined up on John King Boulevard approaching SH 205 in Rockwall. Photo by Adrienne Balkum

At the Sept. 16 Consortium meeting, City Manager Mary Smith and other City of Rockwall staff attended, but they were seated in the audience rather than at the Consortium table with representatives of participating governments.

The meeting did not explain the seating arrangement. The City remains directly involved in discussions involving John King Boulevard and SH 205 Middle, while representatives from Royse City, Fate, Poetry, McLendon-Chisholm, Mobile City and Heath were called upon during governmental updates.

Eight days earlier, Rockwall City Council had met in executive session for legal advice concerning a “transportation consulting services contract.” City Manager Mary Smith later confirmed that no action was taken and the agenda did not identify the consultant.

The County’s September road report also lists ITS, Rockwall County and the City of Rockwall among the parties working on the proposed interim John King/SH 205 arrangement.

Whether the City later brings a transportation consulting agreement forward for public action remains to be seen.

The Outer Loop Hearing Is Coming — With a $1.2 Billion Estimate and No Construction Funding Yet

The Oct. 29 Outer Loop hearing covers only the northern portion of the project.

It is scheduled for Thursday, Oct. 29, from 5:30 to 7:30 pm at Rockwall County Liberty Hall, 1111 E. Yellowjacket Lane in Rockwall.

Rockwall County describes the hearing as concerning the northern section and the Sept. 16 presentation identified it as Phase 1, north of SH 276.

That is not the southern portion involved in the more recent disagreement over the Outer Loop alignment and regional MOU.

Phase 2, however, is already moving. The September report states:

“Halff completed initial evaluation of alignment alternatives for Phase 2.”

Further work is pending a supplemental agreement. So while the southern portion does not yet have a public hearing scheduled, preliminary evaluation of possible alignments has already taken place.

The scale of the project is also significant. The September Consortium project sheet lists the Outer Loop, from County Line Road to SH 205, at an estimated construction cost of $1,206,960,740 with $0 in construction funding.

At the Sept. 16 meeting, Halff said the northern Phase 1 portion alone is expected to cost a little more than $900 million.

Large transportation projects can spend years in environmental review, design, right-of-way acquisition and planning before full construction funding is in place. Even so, the difference between a project being planned and one being fully funded is substantial.

One timing question also remains in the September report. The project table lists:

Schematic Approval (Phase 1): September 2026.

Yet elsewhere, the report says Halff will submit the 100 percent Phase 1 schematic after the Oct. 29 public hearing.

The report does not explain the difference.

Rockwall’s Road Talks Continue Amid Changes at NCTCOG

Todd Little and an excerpt from NCTCOG’s Aug. 27, 2026 Executive Board agenda.
Todd Little alongside an excerpt from NCTCOG’s Aug. 27, 2026 Executive Board agenda.

As Rockwall County reorganizes how its road bond program is managed, significant leadership and governance changes have also unfolded at the regional level.

At its Aug. 27 meeting, the NCTCOG Executive Board went into executive session to discuss personnel matters involving the Executive Director and consult with its attorney.

When the Board returned to open session, Arlington Mayor Jim Ross immediately moved to approve a mutually agreed separation of Executive Director Todd Little’s employment, effective immediately, with “no finding of misconduct or cause.” The motion also authorized severance under Little’s employment agreement and required execution of a release of claims. It passed 8-6.

Earlier in the meeting, former Tarrant County Judge Glen Whitley alleged there was “low morale” at NCTCOG and told the Board that while personnel changes can be difficult, “you have to do what is best for the entire organization.”

The wording of the Board’s motion had a practical effect under Little’s employment agreement. The contract provides 20 weeks of base salary when a termination is not based on misconduct and says no severance is payable for termination based on misconduct.

The agreement lists Little’s annual base salary at $257,500. Based on that figure, 20 weeks of base pay works out to approximately $99,000 before required withholdings.

The motion paired its finding of “no misconduct or cause” with authorization to pay severance under the agreement. What the public record does not reveal is what individual Board members discussed in executive session or why they agreed to those terms.

Little, a former Ellis County judge, became NCTCOG’s executive director in May 2025. His tenure later became part of a broader governance dispute after longtime Transportation Director Michael Morris was removed in April, reinstated shortly afterward, and litigation followed involving NCTCOG, the Regional Transportation Council and Denton County.

In August, NCTCOG and the RTC approved a settlement and new operating structure. Morris is once again serving as NCTCOG’s Director of Transportation.

That regional shift intersects directly with Rockwall County’s transportation work. Outer Loop discussions, John King planning and potential regional transportation funding all involve the RTC/NCTCOG. Nothing in the public record reviewed for this article establishes that Little’s departure changed a Rockwall County agreement.

Rockwall County is making major transportation decisions as its regional partners emerge from litigation, a new operating agreement and a change in executive leadership.

Morris also has a direct connection to the Outer Loop. In October 2025, he gave the Rockwall County Infrastructure Consortium a detailed presentation on the regional project and the planning tools available during the environmental process. I covered that presentation in “What Rockwall County Needs to Know About the Outer Loop Project.”

Nearly a year later, at the Sept. 16 Consortium meeting, Halff’s Matt Craig again referenced Morris’s earlier presentation while discussing the broader regional Outer Loop concept.

The Real Measure Is What Residents Can See

Road projects cross city limits and depend on TxDOT, regional funding, utilities, right-of-way, engineering firms and agreements between governments. That complexity can turn a line on a map into years of planning.

Residents, however, do not experience that complexity as a management chart.

They experience it behind the steering wheel.

And they notice when projected dates move.

In April 2023, the Consortium report showed the Rockwall County portion of SH 205 South as expected to be ready for bidding in June 2024. The September 2026 report now lists a January 2027 ready-to-let date and a June 2027 let date.

There can be legitimate reasons for those changes — utilities, funding, right-of-way, design revisions and coordination among agencies. But to someone sitting in traffic, a later date still means more waiting.

Rockwall County is now committing substantially more money to its road program. The question is whether residents begin to see that investment translate into visible progress.

Which Rockwall County road project matters most to you right now — and what improvement are you waiting to see?